Erilstoun Pontoon Pump

SURFACE
Regis Resources
Garden Well Mine Site, WA

Greenlands was contracted to design, supply, and install a twin 24 km dual-purpose pipeline between the Garden Well mine site and the Erilstoun Pit.

The first pipeline was designed to transfer dewatered water from the Garden Well underground mine to the Erilstoun Pit for settling and storage. The second pipeline was for transferring water from the Erilstoun Pit back to the mill as process water supply. The project also included the installation of a pontoon pump system within the Erilstoun Pit to facilitate water transfer to the mill.

Project Services
  • Twin 450mm HDPE pipelines
  • 150kW pontoon pump system
  • Remote monitoring system
  • Pipeline leak detection system